STEP 1: Request for inspection and submit following to the Fire Department each of them with dimensions
- Site Plan
- Block Plan
- Floor Plan
STEP 2: Inspection of Project/Building by Fire Department.
STEP 3: Present Fire Engineering drawings to the Fire Department.
STEP 4: Apply for Fire Certificate/Permit from the Fire Department.
STEP 5: The Fire Department operates a Risk based system. Categorized as:
- Low Risk Projects
- Medium Risk Projects
- High Risk Projects
STEP 6: The turnaround time for the majority of projects (Low Risk) is five (5) days.
Issued by Fire Safety Directorate.